Change Release roadmap and digital services plan
Glossary
The information supplied here is an outline of Modifications and Change proposals that are scheduled for the next three years. It also outlines enhancements to the Kinnect digital platform over the same period of time.
On this page
Change: Unallocated
- P395: Aligning BSC Reporting with EMR Regulations – an enduring solution
- Status: Assessment phase
- Impacts: CRA, SVAA
- Planning Status: Uncommitted
- Dates: Nov 2022 – Q4 2023
- P410: Changing imbalance price calculations to comply with the Imbalance Settlement Harmonisation regulations
- Status: Assessment phase
- P412: Ensuring non-BM Balancing Services providers pay for non-delivery imbalances at a price that reflects the real-time value of energy
- Status: Assessment phase
- Impacts: BMRS, CRA, SAA, SVAA, TOMAS
- Planning Status: Uncommitted
- Dates: Q2 – Q4 2023
- P415: Facilitating access to wholesale markets for flexibility dispatched by Virtual Lead Parties
- Status: Assessment phase
- Impacts: CRA, SAA, SVAA
- Planning Status: Uncommitted
- Dates: Q2 – Q4 2023
- P425: Amendment to the definition of Shared SVA Meter Arrangement
- Status: Assessment phase
- P426: Combining related BSC Parties’ Energy Indebtedness positions for the Credit Cover Percentage calculation
- Status: Assessment phase
Change: 2021
November
- P399: BSAD Identity Visibility
- Status: approved
- Impacts: BMRS, SAA
- Planning Status: Committed
- Dates: June – Oct 2021
- P421: Align BSC with Grid Code for TERRE Market Suspension
- Status: Report phase
- CP1541: Use of D0004 in BSCP502
- Status: Approved
- CP1544: BSCCo Approved EFR Representative sign-off required for any EFR plan following escalation
- Status: Approved
- CP1545: Introducing Technical Assurance of Metering (TAM) Central Volume Allocation (CVA) Specific Sample audits
- Status: Approved
- CP1547: Clarification on Site Specific LLF Calculation Process for Embedded LDSOs
- Status: Approved
Ad-hoc
- P332: Revisions to the Supplier Hub Principle
- Status: Assessment phase
- P416: Introducing a route of appeal for the Annual Budget in line with the proposals for the Retail Energy Code
- Status: With Authority
Change: 2022
February
- P402: Enabling reform of residual network charging as directed by the Targeted Charging Review
- Status: Approved
- CP1532: Reduce Half Hourly Change of Supplier timelines to meet the Initial Settlement Run
- Status: Approved
- CP1548: Remove constraint requiring BMRS to publish data files in a specific CSV format and structure
- Status: Assessment phase
- CP1549: Amendment of BSCP516 to clarify the criteria for Non-Domestic SVA Metering Systems
- Status: Assessment phase
- CP1551: Measuring Instruments Regulations – updates to BSCP601
- Status: Assessment phase
June
- P375: Settlement of Secondary BM Units using metering behind the site Boundary Point
- Status: Approved
- Impacts: SVAA, DCP, PMP, Portal
- Planning Status: Committed
- Dates: Sept 2021 – June 2022 (June Release)
- CP1527: Increase the minimum data storage capacity for Settlement Outstations and mandate specific selectable integration periods for Metering Codes of Practice
- Status: Approved
- CP1546: Introducing DTC flows to transfer UMS Summary Inventories and Control files
- Status: Approved
- CP1550: Updates to monitoring of voltage failure alarms requirements
- Status: Assessment phase
November
None at present
Change: 2023
February
- P376: Utilising a Baselining Methodology to set Physical Notifications
- Status: Approved
- Impacts: PMP, CRA, DCP, SAA, DM
- Planning Status: Committed
- Dates: Feb 2022 – Q1 2023
- P419: Enhanced Reporting of Demand Data to the NETSO to facilitate BSUoS Reform
- Status: Assessment phase
- Impacts: SVAA
- Planning Status: Committed
- Dates: Feb 2022 – Q1 2023
Industry demand activity
- Provision of Energy Company Data to CSS/REC (Salesforce)
- Dates: Jan – May 2022
Kinnect platform – Settlement Solution
Settlement Solution – SAA Migration (CR469/70)
- Impacts: DCP, SAA, PMP, CRA, CDCA, DM, Comms
- Planning Status: Commit
- Dates: June 2021 – June 2022
Settlement Solution – CDCA migration
- Impacts: CDCA
- Planning Status: Provisional
- Dates: July 2022 – Q4 2023
Settlement Solution – FAA migration
- Impacts: FAA
- Planning Status: Provisional
- Dates: May 2022 – Q1 2023
Kinnect platform – Insights Solution
Insights Release 1 – Fuel Types
- Impacts: DM, Comms, X-Sec
- Planning Status: Committed
- Dates: Aug – Oct 2021
Insights R1.1 – Demand data
- Planning Status: Provisional
- Dates: Nov 2021 – Jan 2022
Insights R1.2 – Margin and Surplus
- Planning Status: Provisional
- Dates: Feb – Apr 2022
Insights Platform – R2 Data Push
- Impacts: Comms, DM, X-Sec
- Planning Status: Provisional
- Dates: May 2022 – Q1 2023
Insights Platform – R3 Integrations/Calculation
- Impacts: BMRS
- Planning Status: Uncommitted
- Dates: Q1 – Q3 2023
Kinnect platform – Customer Solution
Customer Solution R3.2 – Account Management
- Impacts: CRA, FAA, Salesforce
- Planning Status: Provisional
- Dates: July 2021 – Apr 2022
Customer Solution R3.1 – QMij enhancement
- Impacts: PMP, CRA
- Planning Status: Provisional
- Dates: Apr – Aug 2022
Customer Solution Releases 3.3 – 3.5
- Planning Status: Provisional
- Dates: July 2022 – Q1 2023
System upgrades
3rd test environment build
- Planning Status: Committed
- Dates: Jun – Sept 2021
Oracle upgrade (CR2640)
- Impacts: BMRS, CDCA, COMMS, CRA, EAC, ECVAA, PARMS, SAA, SVAA
- Planning Status: Committed
- Dates: Oct 2021 – Oct 2022