CP1258
Formal title: Changes to BSCP520 Following Walkthrough
Current Status
Summary
An Unmetered Supplies Expert Group (UMSEG) was convened in 2007 to discuss UMS issues identified by the BSC Auditor. As part of this work the UMSEG carried out a walkthrough of BSCP520 and identified a series of minor changes to improve processes, correct errors and remove any redundant steps. The proposed changes were issued to industry for comment via DCP0029 in February 2009.
Progression
CP1258 was raised on 27 August 2007, from DCP0029. CP1258 has been issued for Participant Impact Assessment via CPC00642 on 05 September 2008. CP1258 was presented to the SVG on 04 November 2008 for a decision on progression. The SVG approved CP1258 for inclusion in the February 2009 Release. CP1258 was implemented on 26 February 2009 as part of the February 2009 Release.