Code of Practice 7: The Metering of Energy Imports via Low Voltage Circuits Fused at 100 AMPS or Less per Phase for Settlement Purposes
This Code of Practice states the practices that shall be employed, and the facilities that shall be provided for the measurement, recording and collection of the quantities required for Settlement purposes. This Code of Practice specifically applies to Metering and Data Collection Systems (MDCS) to be installed for the metering of energy imports via low voltage circuits fused at 100 AMPS or less per phase.
This Code of Practice states the practices that shall be employed, and the facilities that shall be provided for the measurement, recording and collection of the quantities required for Settlement purposes. This Code of Practice specifically applies to Metering and Data Collection Systems (MDCS) to be installed for the metering of energy imports via low voltage circuits fused at 100 AMPS or less per phase.